15.12.2023

Eiffage Génie Civil teams lay the foundation stone for the extension of the CVE in Saint-Paul (60)

The project includes the construction of a 1,000 m² waste treatment building, a 1,100 m² energy recovery building, an 800 m3 concrete silo, a 450 m² turbo-alternator building, 320 m of track, 170 m² of electrical premises and various ancillary works.

Eiffage Génie Civil teams lay the foundation stone for the extension of the CVE in Saint-Paul (60)

The aim of this project is to increase waste treatment capacity and energy recovery, which is then exported to a heating network.
 
Delivery is scheduled for October 2025!
 
Client: IDDEO
Consortium: Eiffage Génie Civil (leader) and SMB
Project manager: NALDEO
Architect: AT&E

to discover also