24.02.2021
A drinking water reservoir in Occitania signed by Eiffage Génie Civil
The town council of Lézignan-Corbières awarded Eiffage Génie Civil a contract to build a 5,000 m³ drinking water reservoir and pipe work.
Under the project management of the Gaxieu firm, the teams carried out the civil engineering of the circular basins, each with a diameter of 28 m and a capacity of 2,500 m³, as well as a sluice chamber.
This project, which increases the capacity of the city's drinking water supply and fire reserve, required :
- 179 m of prestressed beams,
- 1,337 m² of prestressed pre-slabs,
- 1,258 m³ of concrete
- 1,150 m² of 6.54 m high circular formwork
- 133 t of reinforcement.
Photos Credit: Eiffage Génie Civil
-
25.04.2024Eiffage Civil Engineering has excavated the first 3...The first 3 kilometers of tunnel for Lot 2 have been excavated as part of the construction of the future VL8 collector! The tunnel boring machine, named Béatrice,...
-
24.04.2024Yann Chaussinand, a management controller at Forézienne...Discover Yann's daily life in video!
-
19.04.2024The Foundations teams at Eiffage Civil Engineering...For this expansion project, carried out for the Luberon Shopping Center, the works include: