In the heart of the Seine-Saint-Denis department, on the site of the Stade de France station on line 15, our Résirep and Fondations teams have proposed innovative techniques for the construction of micropiles in very low levels.
- Borehole depth between 49 and 56 m
- Maximum deviation of 1% at drilling
- Installation of the micropile at -25 m from the working platform
In total, we completed 69 micropiles with a diameter of 177.8 mm and a thickness of 12.5 mm; 3,522 m of drilling in diameter 250 mm and 1,800 m of equipment.
Congratulations to our teams involved in this project!
Discover the images of the site in video.
-
04.03.2024Eiffage Civil Engineering connected the two banks of...At the Singrobo-Ahouaty hydroelectric dam, the two banks are now connected, the earthworks phase is completed, and the hydraulic equipment is in place!
-
29.02.2024Eiffage Génie Civil Marine sur le projet Antioquia...Les opérations marines de notre projet Antioquia en Colombie montent en intensité, avec le plus long pieu du projet, 87 m de haut, levé en un seul élément, en toute...
-
29.02.2024Lyon-Turin railway line: 2nd gripper tunnel boring...The ELYOT consortium, for which we are responsible, has just taken delivery of its second and last gripper tunnel boring machine at the Herrenknecht AG plant in...