In order to guarantee support for 15 years, 8 areas weakened by convergence were reinforced by several mobile formwork tools.
With a radius of 5.30 m for 140 tons, these tools have made it possible to concretize the vault per 10 m long stud.
In total, 343 m in counter vault and 333 m in vault were consolidated by blocking rings.
Congratulations to all the teams involved in these major underground works projects !
Discover the installation of the vault formwork tool in pictures !
Consortium : Eiffage Génie Civil, Spie batignolles, Ghella, CMC di Ravenna, COGEIS SPA
Contracting authority : TELT Lyon Turin
-
25.04.2024Eiffage Civil Engineering has excavated the first 3...The first 3 kilometers of tunnel for Lot 2 have been excavated as part of the construction of the future VL8 collector! The tunnel boring machine, named Béatrice,...
-
24.04.2024Yann Chaussinand, a management controller at Forézienne...Discover Yann's daily life in video!
-
19.04.2024The Foundations teams at Eiffage Civil Engineering...For this expansion project, carried out for the Luberon Shopping Center, the works include: