09.04.2026

Toulouse metro: TBM Berthe de Puybusque completes its second breakthrough

The "Berthe de Puybusque" Tunnel Boring Machine (TBM) has successfully completed its second breakthrough, piercing the diaphragm wall of the future Ponts-Jumeaux station. This milestone marks the completion of the first phase of its journey.

This initial 2,539-meter section—out of a total planned excavation of 4,661 meters—was marked by the crossing of Fondeyre station before reaching the finish line at Ponts-Jumeaux.

The journey continues! The TBM will soon be returned to its starting point at La Vache Gare – Le Grand Marché station to begin a second drive. After a meticulous dismantling and repositioning of its cutterhead, it will commence its second excavation phase towards the future Raisin station.

This complex operation is a testament to the expertise of our teams.

Joint Venture: Eiffage Génie Civil (lead contractor) / NGE - BTP
Client: Tisséo Ingénierie - Tisséo Collectivités
Photo credit: Stéphane Bouquet