16.10.2026
30 years after its commissioning, Ævia is rehabilitating the Aussoue dam, located in Saint-Frajou, France
Located at an altitude of 260 meters, this Class B structure serves a strategic mission for irrigation and low-flow augmentation (artificially supplementing watercourses during low-water periods). Our Ævia teams will ensure its regulatory compliance and safety upgrades by carrying out the civil engineering and earthworks package.
The project includes the construction of a new spillway designed to handle exceptional flow rates. This involves using 500 m³ of reinforced concrete on the hydraulic structure, 6,000 m³ of earthworks to raise the dike, as well as strengthening the dam's monitoring system with the addition of new pore water pressure sensors.
The worksite is subject to rigorous environmental protection measures, including the strict demarcation of habitats and an adapted work schedule.
Congratulations to the teams on site for their technical mastery of this demanding structure!
Thank you to Rives & Eaux du Sud-Ouest for their trust!
Joint Venture: Ævia (lead partner) and Bordes.
Credit: Eiffage
-
26.11.2026On the Lot River, Ævia rehabilitates the Mercuès lock...A few kilometers north of Cahors, our Ævia teams have successfully completed an extraordinary project to secure the future of this historic structure, which generates... -
18.11.2026Toulouse Metro: Our TBM Jeanne Marvig has just achieved...Jeanne Marvig has just completed its third breakthrough at the future Saint-Martin - Airbus station. -
17.11.2026In Benin, Eiffage Génie Civil has completed and handed...At the Autonomous Port of Cotonou (PAC), our Eiffage Génie Civil teams have completed and handed over two new phases of work for the basin expansion and the renovation...