The machine has now excavated over 1,650 meters of the 3,854 meters planned from its starting point at the Colomiers Gare shaft.
The TBM is now advancing towards the Saint-Martin du Touch station, with the final objective of reaching the Laporte shaft.
We wish the Jeanne Marvig TBM and its crew continued success for the remainder of their journey.
Joint Venture: Eiffage Génie Civil (lead partner) / NGE - BTP
Project Management: Tisséo Ingénierie - Tisséo Collectivités
Credit: Stéphane BOUQUET
to discover also
-
22.07.2026In the heart of the Mont-Blanc massif, Ævia applies...In the municipality of Megève, Ævia has successfully renovated the Cassioz bridge. -
21.07.2026Two new tunnel boring machines for Line 15 EastThis Friday, July 17, 2026, Eiffage Génie Civil, together with the project owner Société des grands projets, has officially accepted two new tunnel boring machines... -
17.07.2026The 37th edition of the Baticup was marked by another...Two Eiffage Génie Civil crews were involved in this frigate which took place in Quiberon Bay departing from the port of La Trinité-sur-Mer (56).