![Eiffage Civil Engineering connected the two banks of the Singrobo-Ahouaty dam in Ivory Coast](/files/live/sites/genie-civil/files/actualites/capture_singrobo-ahouaty-rives-connectees_1.jpg)
- Installation of a rock fill embankment over 1,400 meters, involving the excavation of 800,000 cubic meters of materials directly from the site.
- Commencement of the commissioning of hydraulic gates assembled by STPH - HWP Group.
- Assembly of the 2 horizontal axis Kaplan turbines by GE Renewable Energy: in progress.
It's worth noting that this dam is intended to deliver a power of 44 megawatts (MW) to the Ivorian interconnected grid. It will also supply power to the surrounding villages: Singrobo, Ahouaty, Ahénémou 2, Pacobo, and N’Dènou.
A design-build project with RMT from Eiffage Energy Systems, on behalf of Ivoire Hydro Energy, the project's concessionaire.
Explore the images of this project.
-
04.07.2024Discover the behind-the-scenes video of the refurbishment...The Jeanne-Marvig tunnel boring machine arrived at the Toulouse Metro Line C construction site at the end of June. Discover the behind-the-scenes of its refurbishment...
-
01.07.2024In Toulouse, Eiffage Génie Civil inaugurates the Robert...Our teams participated in the inauguration of the Robert Poujade footbridge, formerly Rapas, on June 22, 2024, in the presence of Jean-Luc Moudenc, Mayor of Toulouse...
-
27.06.2024The Cutterhead of the Tunnel Boring Machine Jeanne...At the end of June, on the Toulouse Metro Line C construction site, the tunnel boring machine Jeanne Marvig was unveiled at the Colomiers Gare shaft site. The event...