In Vitry-sur-Seine (94), Eiffage Génie Civil is participating in the "Ardoines Ramp" project
The project, which is part of the municipality's modernisation plan, involves building a hydraulic compensation structure under the west ramp of the Ardoines crossing, and will also address the risk of flooding in the event of the Seine flooding.
Following a general pre-digging operation, the Foundations teams drilled the 175 anchor piles for the pool, ranging in diameter from 800 mm to 1200 mm, over a length of 17 m.
Once the roof slab covering almost 4,000 m² and its waterproofing had been completed, work continued on the underside with the mole excavation of 12,000 m³ of earth, the construction of a shotcrete perimeter wall and the invert of the structure.
By changing the phasing of the work, the overall schedule was shortened by almost a month, and 70% of the excavated material was reused as backfill.
The "top and down" method used - structure then mole earthworks - is helping to reduce the carbon footprint of this operation.
Completion is scheduled for June 2024!
-
25.04.2024Eiffage Civil Engineering has excavated the first 3...The first 3 kilometers of tunnel for Lot 2 have been excavated as part of the construction of the future VL8 collector! The tunnel boring machine, named Béatrice,...
-
24.04.2024Yann Chaussinand, a management controller at Forézienne...Discover Yann's daily life in video!
-
19.04.2024The Foundations teams at Eiffage Civil Engineering...For this expansion project, carried out for the Luberon Shopping Center, the works include: